Steam Tug William C Daldy

Year 2000 Major Overhaul

Posted in 2000 Major Hull Plating on May 1st, 2009 by Webmaster

Thanks to a generous grant from the New Zealand Lotteries Commission in 2000, major hull plating underneath the boilers was carried out.

alex plating Year 2000 Major Overhaul
Marine Superintendent Alex Franklin inspecting progress
© Godfrey Down

bunker1 Year 2000 Major Overhaul
Bunker with new ribs
© Godfrey Down

firstcut Year 2000 Major Overhaul
first cut of the old tired plates
© Godfrey Down

half polisbhed prop Year 2000 Major Overhaul
half polished prop
© Godfrey Down

new bilge Year 2000 Major Overhaul
New bilge plates
© Godfrey Down

new bunkers Year 2000 Major Overhaul
New bunkers…no more rust
© Godfrey Down

nzherald2000 Year 2000 Major Overhaul
nzherald2000
© Godfrey Down

plating Year 2000 Major Overhaul
plating
© Godfrey Down

plating bunkers Year 2000 Major Overhaul
plating bunkers
© Godfrey Down

plating gasbottles Year 2000 Major Overhaul
more gasbottles to cut out rust
© Godfrey Down

plating gasbottles2 Year 2000 Major Overhaul
more gasbottles to cut out rust
© Godfrey Down

platngribs Year 2000 Major Overhaul
Plating and rib renewal
© Godfrey Down

proprm1 Year 2000 Major Overhaul
View from astern
© Godfrey Down

propshaft Year 2000 Major Overhaul
Propshaft removal and seal renewal
© Godfrey Down

props polished Year 2000 Major Overhaul
props polished
© Godfrey Down

prp removed Year 2000 Major Overhaul
Prop and cowling removed
© Godfrey Down

2002 Major Overhaul

Posted in 2002 Engine Room Plating on May 1st, 2009 by Webmaster

Thanks to a generous grant from the ASB Community Trust in 2002, major hull plating on the port side of the engine room was carried out. A new seawater intake for the condenser was fabricated and the bilge and general purpose/fire pump were overhauled. General hull cleaning and painting were also carried out.

200204 1 2002 Major OverhaulView of dented bow to be repaired. That darn wharf just keeps getting in the way! Hull of New Lyttelton Tug Blackadder in background during fabrication!
© Courtney Edmonds

200204 2 2002 Major OverhaulWasted anodes out perhaps not wasted enough.
© Courtney Edmonds

200204 3 2002 Major OverhaulStarboard mid section after waterblasting. Hull of New Lyttelton Tug Blackadder in background during fabrication!
© Courtney Edmonds

200204 4 2002 Major OverhaulPropeller view MV Atlantic Trader (now scrapped) in background.
© Courtney Edmonds

200204 5 2002 Major OverhaulPropeller view.
© Courtney Edmonds

200204 6 2002 Major OverhaulPort rubbing strake section that was replaced with a large piece of macrocarpa.
© Courtney Edmonds

200204 7 2002 Major OverhaulAn anode that has done its job well.
© Courtney Edmonds

200204 8 2002 Major OverhaulNew hull plates and ribs for th engine room.
© Courtney Edmonds

200204 9 2002 Major OverhaulNew bow section below bull ring cut and ready for new section to be welded.
© Courtney Edmonds

200204 91 2002 Major OverhaulCut Rotten Hull behind service pump and seawater intake for condenser.
© Courtney Edmonds

200204 92 2002 Major OverhaulNew plates and seawater intake primed.
© Courtney Edmonds

200204 93 2002 Major OverhaulPropeller coated with clear antifoul product.
© Courtney Edmonds

200204 94 2002 Major OverhaulStern section showing new anodes in place.
© Courtney Edmonds